Plug-in solar

Plug-In Solar and the Smart Export Guarantee: Can You Get Paid?

Most plug-in solar kits do not qualify for the Smart Export Guarantee, which requires MCS certification. What your exports are worth and how to get paid.

By Voltgeber Editorial Team Updated Last verified 8 min read Applies to United Kingdom
Plug-In Solar and the Smart Export Guarantee: Can You Get Paid?

Key facts

  • The Smart Export Guarantee requires solar installations up to 50 kW to be certified under MCS or an equivalent scheme, which a self-installed plug-in kit normally is not.
  • SEG payments also need a meter that records exports half-hourly and an export MPAN, in practice a working smart meter.
  • In the government's July 2026 model, an 800 W kit tilted south exports about 262 kWh a year, and a vertical east or west kit about 106 kWh.
  • At an export rate of 12p per kWh, those exports are worth about £31 and £13 a year; the main saving comes from electricity used at home.
  • Since October 2026, at least one supplier has offered its own export tariff to customers who bought its plug-in kit, outside the SEG rules.

Most plug-in solar kits do not qualify for the Smart Export Guarantee (SEG). The scheme requires solar installations to be certified under the Microgeneration Certification Scheme (MCS) or an equivalent, and a self-installed kit has no certificate. Surplus power still flows to the grid, unpaid unless your supplier offers its own export tariff. Either way, an 800 W kit’s exports are worth tens of pounds a year at most.

How the Smart Export Guarantee works

The SEG has run in Great Britain since 1 January 2020, replacing the export part of the Feed-in Tariff, which closed to new applicants in 2019. Under it, the larger electricity suppliers, called SEG licensees, must offer at least one tariff that pays small generators for each kilowatt-hour they export. Ofgem administers the scheme; suppliers set their own rates, which must always be above zero.

Ofgem’s scheme page lists solar PV among the eligible technologies, for installations up to 5 MW located in Great Britain. The detail that matters for plug-in solar sits in the eligibility checks suppliers must carry out:

SEG requirement What it means A typical plug-in kit
Eligible technology Solar PV, wind, hydro, anaerobic digestion, micro-CHP Meets it
Location Great Britain Meets it in England, Scotland and Wales
Certification (solar up to 50 kW) MCS certificate, or an installation and installer certified to an equivalent standard such as Flexi-Orb Does not meet it: self-installed, no certificate
Metering Export meter capable of half-hourly readings, with an export MPAN registered in settlement Possible with a working smart meter
Not already paid for exports No Feed-in Tariff export payments on the same installation Normally meets it

The certification row is the obstacle. MCS certifies installers and products for permanently wired systems; a plug-in kit is designed to be installed by an ordinary person through a socket, with no installer at all. The government’s final impact assessment of July 2026 states the position plainly: SEG requires a half-hourly export meter and MCS-certified installation, and this is “likely not to apply in the first instance for many plug-in solar installers”. A later paragraph adds that without an MCS-accredited installation, consumers are not entitled to the SEG.

What your exports are actually worth

The question matters less than it seems, because a plug-in kit exports little. The government modelled an 800 W kit for a household that is home during the day and uses the GB average of 3,323 kWh a year. Subtracting what the home uses from what the panels produce gives the exports:

Set-up (government model) Generated a year Used at home Exported Value of exports at 12p/kWh Value of home use at 26.32p/kWh
30° tilt, facing south 690 kWh 428 kWh 262 kWh about £31 about £113
Vertical, facing east or west 378 kWh 272 kWh 106 kWh about £13 about £72

The 12p figure is the flat rate Octopus Energy published for its Outgoing tariff in November 2026, used here only as a reference point. The 26.32p figure is the Ofgem price cap average unit rate for October to December 2026. Every unit you use at home is worth roughly twice what a typical export tariff pays, which is why the savings from plug-in solar come almost entirely from self-consumption.

Octopus itself tells plug-in customers to expect export earnings of no more than about £50 a year. A household that is out all day exports more than the government’s example, so its export income would sit towards the top of that range, and its bill saving lower.

€
A unit used at home saves the full unit rate; a unit exported earns an export rate, if you have one, and nothing if you do not.

Exporting with no export tariff

Without an export tariff, surplus electricity simply flows out through your meter into the local network, where a neighbour uses it. Nobody pays you, and nothing goes wrong. The power is not wasted from the system’s point of view, and the government’s impact assessment counts it as a benefit for emissions and the network.

Your meter decides what you see on the bill:

  • Smart meters (SMETS1 and SMETS2) record imports and exports on separate registers. Exports never reduce your import reading, so you are billed exactly for what you take from the grid.
  • Older meters may not record exports in a way your supplier can use. Some older electromechanical meters are reported to turn backwards when power flows out, which is not a recognised way of being paid for exports. Tell your supplier you have a generating device and ask how it will be metered; it may offer a smart meter.

The notification to your distribution network operator is a separate duty and does not create any payment. Our guide to telling your DNO about plug-in solar explains it.

Ways to get paid for exports in 2026

As of 3 November 2026, three routes exist, none of them through the SEG for a standard self-installed kit.

A supplier tariff for its own plug-in kits. Octopus Energy, which was selling plug-in bundles by September 2026, says customers who buy the bundle from Octopus and take their electricity from Octopus can join one of its export tariffs once the kit is installed and notified to the network operator. Its Outgoing tariff paid a flat 12p per kWh in November 2026. Octopus says panels bought from other retailers are not eligible for that route. This is a voluntary commercial offer, not the SEG, and it can change.

A supplier’s non-MCS export route. Octopus also runs a paid route for systems without MCS certification. Its help page lists a £250 fee and three documents: an Electrical Installation Certificate, a Building Regulations certificate of compliance (not applicable in Scotland) and a DNO acceptance letter. Those documents belong to a permanently wired installation by an electrician, so the route does not suit a plug-in kit, and the fee alone exceeds several years of plug-in export income.

Asking your own supplier. Smaller suppliers can offer export tariffs voluntarily, and terms differ. If you want to try, ask in writing whether they will pay for exports from a plug-in device that is listed on the ENA Type Test Register and notified to your DNO, and what evidence they need.

  1. Check your meter. You need a working smart meter that sends half-hourly export readings. If you have an older meter or a smart meter in “dumb” mode, ask your supplier to fix that first.

  2. Notify your network operator. Use the route on your kit’s label and keep the confirmation; any export offer will ask for it.

  3. Ask your supplier the specific question. Name the device, its ENA register listing and its 800 W rating, and ask whether an export tariff is available without MCS certification.

  4. Get an export MPAN set up. If the supplier agrees, it requests the export reference number from your network operator; you do not normally apply for it yourself.

  5. Compare before you switch. A better export rate rarely justifies a worse import rate, because you import far more units than a plug-in kit exports.

Mistakes to avoid

  • Buying a kit for the export income. At 12p per kWh, even a well-placed kit earns around £30 a year from exports. Judge the purchase on what it saves you at home.
  • Switching supplier for the export tariff alone. Check the import unit rate and standing charge first; a penny more per imported unit can cost more than the whole export income.
  • Paying for certification you do not need. No scheme certifies a self-installed plug-in kit for the SEG, and a fee to “register” your kit for export payments is a warning sign.
  • Assuming a battery would fix it. Storing surplus for the evening is worth more than exporting it, but batteries are excluded from plug-in kits under the current rules; see plug-in solar with a battery.

Rooftop solar, plug-in solar and the SEG compared

Plug-in kit MCS-certified rooftop system
Typical size Up to 800 W output 3 to 5 kW
Installed by You, through a socket MCS-certified installer
SEG eligible Normally not Yes, with a suitable meter
Typical yearly exports About 100 to 260 kWh in the government model Often well over 1,000 kWh
Export income at 12p/kWh About £13 to £31 Often £100 or more

The gap explains why the SEG matters a great deal for rooftop systems and very little for plug-in kits. A rooftop system routinely produces more than the house uses at midday; an 800 W kit often does not.

What could change

The government’s July 2026 consultation response records that respondents called for reform of the SEG to maximise the benefit of plug-in solar. The government did not commit to any change. Its impact assessment expects that some plug-in users may seek an export tariff, “contingent on registering their devices” with their network operator, depending on developments in the retail energy market. In other words, the network notification that every plug-in user now makes could become the basis for export payments later, but as of November 2026 that is a possibility, not a policy.

Northern Ireland has no SEG, and plug-in solar is not yet lawful to use there; see is plug-in solar legal in the UK.

Next steps

Frequently asked questions

Can I get the Smart Export Guarantee with plug-in solar?

Usually not. SEG suppliers must check that a solar installation up to 50 kW is certified under the Microgeneration Certification Scheme or an equivalent, and plug-in kits are installed by householders without MCS certification. The government's own impact assessment says this is likely not to apply for many plug-in users at first.

Is there any way to get paid for plug-in solar exports?

Only if a supplier chooses to offer an export tariff outside the SEG rules. As of November 2026, Octopus Energy says customers who bought its plug-in bundle and take their electricity from Octopus can join its export tariffs. Ask your own supplier; the answer differs by company.

How much would I earn from exporting plug-in solar power?

Not much. The government's model has an 800 W south-facing kit exporting about 262 kWh a year; at 12p per kWh that is roughly £31. A vertical east or west kit exports about 106 kWh, worth around £13. Using the power at home saves about 26p per kWh instead.

Does my meter run backwards when plug-in solar exports?

A smart meter does not. It records imported and exported electricity on separate registers, so exports never reduce the import reading. If you still have an older meter, tell your supplier you have generation and ask how it will be metered.

Do I need an export MPAN for plug-in solar?

Only if you want an export tariff. The export MPAN is the reference number that lets a supplier pay for exported units, and the supplier arranges it with your network operator. For simply using a plug-in kit, the DNO notification is all you need.

Will the Smart Export Guarantee change for plug-in solar?

Possibly, but nothing had been announced by 3 November 2026. Respondents to the government's June 2026 consultation called for SEG reform, and the impact assessment says access to export tariffs may depend on how the retail energy market develops.

Sources

  1. Smart Export Guarantee (SEG) Ofgem, accessed Nov 3, 2026
  2. SEG: Guidance for Generators (December 2019) Ofgem, accessed Nov 3, 2026
  3. Smart Export Guarantee (SEG): earn money for exporting the renewable electricity you have generated GOV.UK, accessed Nov 3, 2026
  4. Plug-in solar final stage impact assessment (16 July 2026), paragraphs 32 to 35 and 61 Department for Energy Security and Net Zero, accessed Nov 3, 2026
  5. Plug-in solar: government response (July 2026), Section E Department for Energy Security and Net Zero, accessed Nov 3, 2026
  6. Changes to energy price cap between 1 October and 31 December 2026 Ofgem, accessed Nov 3, 2026
  7. Everything you need to know about plug-in solar panels (4 June 2026) Octopus Energy, accessed Nov 3, 2026
  8. Outgoing Octopus Octopus Energy, accessed Nov 3, 2026
  9. Export without MCS Octopus Energy, accessed Nov 3, 2026

This guide is general information, not legal, tax or electrical advice. Your utility, state and local code have the final say.